Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

Public Works

Department

Project Title

Municipal Building Envelope Waterproofing

Status

Existing

Project Description

This project will provide funding to address historical water intrusion issues on the exterior of the Municipal Building. This project will also include the replacement of the roof membrane on the main section of the building.

Goal Addressed

Community Wellbeing

Estimated Start Date

Estimated End Date

Summer 2026

Fall 2027

Total Five-Year CIP

Funded through 6/30/2026

Funding Sources

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

General Fund

$90,000 $550,000

90,000

$0

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

550,000

$550,000

$0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0

VDOT Smart Scale

Other/Grants Total Sources

$640,000

$90,000 $550,000

$0

$0

$0

$0 $550,000

Total Five-Year CIP

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Expenditure Type Design/Engineering

Total Project Cost

$90,000 $550,000

90,000

$0

Construction

550,000

$550,000

Land Acquisition

$0 $0

$0 $0

Vehicles/Equipment

Total Uses

$640,000

$90,000 $550,000

$0

$0

$0

$0 $550,000

Operating Impact

No additional operational costs are anticipated.