PROJECT DETAILS/COST ESTIMATES
Public Works
Department
Project Title
Major Facilities Repair and Maintenance
Status
Existing
Project Description
This project funds annual miscellaneous improvements to town-owned buildings in accordance with annual safety, security and condition inspections. Typical improvements funded by this project include gutter/downspout repairs, roof repairs, door and window replacements, heating/air conditioning ductwork repairs, alarm and access control system upgrades and site drainage improvements. For FY27, the continuing CIP project titled Rental Property Maintenance, has been combined with Major Facilities Repair and Maintenance, adding $40,000 to the annual project funding.
Goal Addressed
Community Wellbeing
Estimated Start Date
Estimated End Date
Continuing
Continuing
Funded through 6/30/2026
Total Five Year CIP
Funding Sources
Total Project Funding
FY2027 FY2028 FY2029 FY2030 FY2031
General Fund
$950,000 Continuing
190,000 190,000 190,000 190,000 190,000 $950,000
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
VDOT Smart Scale
Other/Grants Total Sources
$950,000
$0 $190,000 $190,000 $190,000 $190,000 $190,000 $950,000
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Total Five Year CIP
Expenditure Type Design/Engineering
Total Project Cost
$50,000 Continuing $650,000 Continuing
10,000 10,000 10,000 10,000 10,000 $50,000 130,000 130,000 130,000 130,000 130,000 $650,000
Construction
Land Acquisition
$0
$0
Equipment Total Uses
$250,000 Continuing
50,000 50,000 50,000 50,000 50,000 $250,000 $0 $190,000 $190,000 $190,000 $190,000 $190,000 $950,000
$950,000
Operating Impact
No additional operational costs are anticipated.