Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

Public Works

Department

Project Title

Infill Curb, Gutter, and Sidewalk Construction

Status

Existing

Project Description

This continuing project funds the construction of infill, curb, gutter and sidewalk that is not eligible in the VDOT Revenue Sharing program.

Goal Addressed

Transportation

Estimated Start Date

Estimated End Date

Continuing

Continuing

Total Five-Year CIP

Funded through 6/30/2026

Funding Sources

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

General Fund

$100,000 Continuing

20,000 20,000 20,000 20,000 20,000 $100,000

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0

VDOT Smart Scale

Other/Grants Total Sources

$100,000

$0 $20,000 $20,000 $20,000 $20,000 $20,000 $100,000

Total Five-Year CIP

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Expenditure Type Design/Engineering

Total Project Cost

$100,000 Continuing

20,000 20,000 20,000 20,000 20,000 $100,000

Construction

$0 $0 $0

$0 $0 $0

Land Acquisition

Vehicles/Equipment

Total Uses

$100,000

$0 $20,000 $20,000 $20,000 $20,000 $20,000 $100,000

Operating Impact

No additional operational costs are anticipated.

Town of Blacksburg

58

FY 2027-2031 Adopted

Made with FlippingBook Digital Proposal Maker