Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

Sustainability

Department

Toms Creek Restoration

Project Title

Status

Existing

Project Description

The Town is advancing a multi-phase restoration project at Heritage Park and Toms Creek to improve ecological function, enhance stormwater management, and increase recreational opportunities, including the construction of a secondary pedestrian bridge. The creek restoration will draw on the successes of the StREAM Lab on Stroubles Creek at Virginia Tech and is expected to provide long-term environmental and community benefits. Design and engineering must be completed before the Town can apply for grant funding to implement the creek restoration. The proposed timeline and project phasing are as follows: Heritage Park Restoration – Initial restoration underway, funded by Virginia Environmental Endowment (VEE) grant through FY2026. Eight year invasive species management to ensure native plant establishment is requested through a separate CIP project.

Heritage Park Wetland Delineation – Funded and completed via FY2025 operating budget.

Toms Creek Restoration Design and Engineering – Proposed CIP funding in FY2027.

Toms Creek Restoration Construction – Must be completed within five years of approved wetland delineation per Army Corps of Engineers; VEE grant application planned for January 2026.

Goal Addressed

Sustainability

Estimated Start Date

Estimated End Date

Summer 2027

Summer 2028

Total Five-Year CIP $100,000

Funded through 6/30/2026

Funding Sources General Fund

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

$100,000

$100,000

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0

VDOT Smart Scale

Other/Grants Total Sources

$100,000

$0 $100,000

$0

$0

$0

$0 $100,000

Total Five-Year CIP $100,000

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Expenditure Type Design/Engineering

Total Project Cost

$100,000

100,000

Construction

$0 $0 $0

$0 $0 $0

Land Acquisition

Vehicles/Equipment

Total Uses

$100,000

$0 $100,000

$0

$0

$0

$0 $100,000

Operating Impact

Town of Blacksburg

33

FY 2027-2031 Adopted

Made with FlippingBook Digital Proposal Maker