Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
Sustainability
Department
Toms Creek Restoration
Project Title
Status
Existing
Project Description
The Town is advancing a multi-phase restoration project at Heritage Park and Toms Creek to improve ecological function, enhance stormwater management, and increase recreational opportunities, including the construction of a secondary pedestrian bridge. The creek restoration will draw on the successes of the StREAM Lab on Stroubles Creek at Virginia Tech and is expected to provide long-term environmental and community benefits. Design and engineering must be completed before the Town can apply for grant funding to implement the creek restoration. The proposed timeline and project phasing are as follows: Heritage Park Restoration – Initial restoration underway, funded by Virginia Environmental Endowment (VEE) grant through FY2026. Eight year invasive species management to ensure native plant establishment is requested through a separate CIP project.
Heritage Park Wetland Delineation – Funded and completed via FY2025 operating budget.
Toms Creek Restoration Design and Engineering – Proposed CIP funding in FY2027.
Toms Creek Restoration Construction – Must be completed within five years of approved wetland delineation per Army Corps of Engineers; VEE grant application planned for January 2026.
Goal Addressed
Sustainability
Estimated Start Date
Estimated End Date
Summer 2027
Summer 2028
Total Five-Year CIP $100,000
Funded through 6/30/2026
Funding Sources General Fund
Total Project Funding
FY2027 FY2028 FY2029 FY2030 FY2031
$100,000
$100,000
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
VDOT Smart Scale
Other/Grants Total Sources
$100,000
$0 $100,000
$0
$0
$0
$0 $100,000
Total Five-Year CIP $100,000
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Expenditure Type Design/Engineering
Total Project Cost
$100,000
100,000
Construction
$0 $0 $0
$0 $0 $0
Land Acquisition
Vehicles/Equipment
Total Uses
$100,000
$0 $100,000
$0
$0
$0
$0 $100,000
Operating Impact
Town of Blacksburg
33
FY 2027-2031 Adopted
Made with FlippingBook Digital Proposal Maker