Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
Transit
Department
Project Title
Support Vehicle Replacement and Expansion Program
Status
Existing
Project Description
Blacksburg Transit has developed a replacement/expansion program for support vehicles, which meets Transit's needs. The proposed schedule for support vehicle replacement and expansion is as follows:
Year
Description
Number Total Type
Category
FY2027 FY2028 FY2029 FY2030 FY2031
None Scheduled
Maintenance
2
2 Replacement
Heavy Duty
Admin / Operations / Maintenance
4 / 2 / 1 7 Replacement
Light Duty / Light Duty / Light Duty
None Scheduled None Scheduled
Blacksburg Transit may extend the replacement schedule for some vehicles if warranted, based on a periodic review of mileage, condition and age. Costs are based on gas/diesel vehicle prices. If adequate funding is available, electric vehicles may be substituted for gas/diesel vehicles. Changes in service and funding may alter future vehicle needs, sizes and types. If grants are unavailable, the project may be deferred.
Goal Addressed
Transportation
Estimated Start Date
Estimated End Date
Continuing
Continuing
Funded through 6/30/2026
Total Five Year CIP $138,600 $428,300
Funding Sources Federal Funds
Total Project Funding
FY2027 FY2028 FY2029 FY2030 FY2031
Continuing Continuing Continuing Continuing
Continuing Continuing Continuing Continuing
50,000 88,600 154,600 273,700 22,800 40,300
State Funds Local Funds Total Sources
$63,100
$0 $227,400 $402,600
$0
$0 $630,000
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Total Five Year CIP
Expenditure Type Design/Engineering
Total Project Cost
$0 $0 $0
Construction
Land Acquisition
Vehicles/Equipment
Continuing Continuing
Continuing Continuing
227,400 402,600
$630,000
Total Uses
$0 $227,400 $402,600
$0
$0 $630,000
Operating Impact
No additional operating costs are anticipated.
Town of Blacksburg
140
FY 2027-2031 Adopted
Made with FlippingBook Digital Proposal Maker