PROJECT DETAILS/COST ESTIMATES

Transit

Department

Project Title

Bus Pull-Offs

Status

Existing

Project Description

This project provides funding for bus pull-offs to pick up and drop off passengers without blocking travel lines. Pull-offs are most appropriate at high volume bus stops and on busy streets to improve safety for bus riders, bike riders and automobile drivers. The planned projects include new pull-offs and extensions of existing pull-offs to accomodate 60-foot buses.

Year

Description

FY2027 FY2028 FY2029 FY2030 FY2031

None Scheduled

Toms Creek Road at Hunt Club Road, SB, Stop #1338 - Build Phase

Patrick Henry Corridor - Design Phase Patrick Henry Corridor - Build Phase Prices Fork Corridor - Design Phase

If grants are unavailable, the project may be deferred.

Goal Addressed

Transportation

Estimated Start Date

Estimated End Date

Continuing

Continuing

Funded through 6/30/2026

Total Five Year CIP

Funding Sources Federal Funds

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

Continuing Continuing Continuing Continuing

Continuing Continuing Continuing Continuing

44,000 6,600 46,200

8,800 $105,600

State Funds Local Funds Total Sources

136,000 20,400 142,800 27,200 $326,400

20,000 3,000 21,000

4,000 $48,000

$0 $200,000 $30,000 $210,000 $40,000 $480,000

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering Land Acquisition Vehicles/Equipment Construction

Total Project Cost

Continuing Continuing

Continuing Continuing

30,000

40,000 $70,000

200,000

210,000

$410,000

$0 $0

Total Uses

$0 $200,000 $30,000 $210,000 $40,000 $480,000

Continuing

Continuing

Operating Impact

No additional operating costs are anticipated.