PROJECT DETAILS/COST ESTIMATES
EGIS
Department
Project Title
Harding Avenue Phase IIA Improvements
Status
Existing
Project Description
This project will complete the construction of new larger replacement sewers in the upper portion of the Harding Avenue sewershed between Patrick Henry Drive and the Harding Elementary School to increase capacity.
Goal Addressed
Neighborhood Quality
Estimated Start Date
Estimated End Date
7/1/2027
12/30/2028
Total Five Year CIP
Funded through 6/30/2026
FY2027 FY2028 FY2029 FY2030 FY2031
Funding Sources General Fund
Total Project Funding
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$5,480,000
5,480,000
$5,480,000
VDOT Smart Scale
Other/Grants Total Sources
$5,480,000
$0
$0 $5,480,000 $0
$0
$0 $5,480,000
Total Five Year CIP
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Expenditure Type Design/Engineering
Total Project Cost
$30,000
30,000
$30,000
Construction
$5,450,000
5,450,000
$5,450,000
Land Acquisition
$0 $0
$0 $0
Vehicles/Equipment
Total Uses
$5,480,000
$0
$0 $5,480,000 $0
$0
$0 $5,480,000
Operating Impact
This project will mitigate sewer overflows, provide needed capacity for new development, and reduce operating costs by reducing I & I.