Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

EGIS

Department

Project Title

Neil Street Tank Rehabilitation and Maintenance

Status

Existing

Project Description

The Neil Street water tank was inspected by Tank Industry Consultants in 2021 for structural, sanitary, safety, and operational deficiencies. The evaluation concluded the tank requires interior shell and floor painting to address corrosion and pitting and additional repairs to address safety and sanitary issues. This project will address the deficiencies outlined in the report including cleaning and painting the interior and exterior of the tank, pit and foundation repairs, safety modifications, and operational repairs.

Goal Addressed

Community Wellbeing

Estimated Start Date

Estimated End Date

Fall 2024

Fall 2029

Funded through 6/30/2026

Total Five Year CIP

Funding Sources General Fund

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

$0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$1,300,200

635,000

665,200

$665,200

VDOT Smart Scale

Other/Grants Total Sources

$1,300,200

$635,000

$0 $665,200

$0

$0

$0 $665,200

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering Land Acquisition Vehicles/Equipment Construction

Total Project Cost

$80,000

30,000 605,000

50,000 615,200

$50,000 $615,200

$1,220,200

$0 $0

$0 $0

Total Uses

$1,300,200

$635,000

$0 $665,200

$0

$0

$0 $665,200

Operating Impact

No operating impact is anticipated.

Town of Blacksburg

124

FY 2027-2031 Adopted

Made with FlippingBook Digital Proposal Maker