Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
EGIS
Department
Project Title
Laurel Ridge Waterline Replacement and Water Quality Upgrades
Status
Existing
Project Description
This project will evaluate the system and replace existing waterlines in the Laurel Ridge Subdivision to improve accessibility and reliability. Existing waterlines are located in steep mountainous terrain, crossing a ravine and wet weather creek that are inaccessible to equipment for maintenance and repairs. The existing waterline layout has a dead-end that creates water quality issues. This project will provide a waterline design and construction to improve water quality and relocation to more accessible areas. The project includes a PER(Preliminary Engineering Report) in FY2027, design in FY2028, and construction in FY2029.
Goal Addressed
Neighborhood Quality
Estimated Start Date
Estimated End Date
Fall 2026
Fall 2029
Funded through 6/30/2026
Total Five Year CIP
Funding Sources General Fund
Total Project Funding
FY2027 FY2028
FY2029 FY2030 FY2031
$0
$0
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$3,045,000 $200,000
3,045,000
$3,045,000 $200,000
50,000 150,000
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
VDOT Smart Scale
Other/Grants Total Sources
$3,245,000
$0 $50,000 $150,000 $3,045,000
$0
$0 $3,245,000
Appropriated through 6/30/2026 FY2027 FY2028
Total Five Year CIP
Expenditure Type Design/Engineering
Total Project Cost
FY2029 FY2030 FY2031
$200,000 $3,045,000
50,000 150,000
$200,000 $3,045,000
Construction
3,045,000
Land Acquisition
$0 $0
$0 $0
Vehicles/Equipment
Total Uses
$3,245,000
$0 $50,000 $150,000 $3,045,000
$0
$0 $3,245,000
Operating Impact