Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

EGIS

Department

Project Title

Glade Road Culvert Repair

Status

New

Project Description

The Glade Road culvert over Toms Creek needs repair to extend its lifespan. There is a 66 square foot section of the corrugated metal arch culvert that has lost 90 to 100 percent of the structure. The repair includes replacement of the sections with advanced loss and applying a protective coating to the entire culvert.

Goal Addressed

Community Wellbeing

Estimated Start Date

Estimated End Date

8/1/2026

10/1/2026

Funded through 6/30/2026

Total Five Year CIP

Funding Sources

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

General Fund

$0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$191,000

0 191,000

$191,000

VDOT Smart Scale

Other/Grants Total Sources

$191,000

$0 $191,000

$0

$0

$0

$0 $191,000

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering

Total Project Cost

$0

$0

Construction

$191,000

191,000

$191,000

Land Acquisition

$0 $0

$0 $0

Vehicles/Equipment

Total Uses

$191,000

$0 $191,000

$0

$0

$0

$0 $191,000

Operating Impact

Reduces future maintenance

Town of Blacksburg

114

FY 2027-2031 Adopted