Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
EGIS
Department
Project Title
Broce Drive Culvert Repair
Status
New
Project Description
Replacing a stormwater system is necessary when the aging infrastructure becomes physically damaged or overwhelmed by capacity issues due to increased flows and urbanization. Joint separation allows soil to be washed away, creating voids that lead to ground instability and potential road collapse. This separation also creates entry points for tree roots and can lead to blockages, backups, and the eventual failure of the pipe system. This project aims to restore the separation at the existing 54-inch concrete pipe to avoid impacts to Broce Drive and install a headwall to stabilize the pipe in the future.
Goal Addressed
Community Wellbeing
Estimated Start Date
Estimated End Date
7/1/2027
6/30/2028
Funded through 6/30/2026
Total Five Year CIP
Funding Sources General Fund
Total Project Funding
FY2027
FY2028
FY2029 FY2030 FY2031
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
General Obligation Bonds Water & Sewer Fund
Stormwater Fund Solid Waste Fund
$270,000
20,000
250,000
$270,000
VDOT Revenue Sharing
VDOT Smart Scale
Other/Grants Total Sources
$270,000
$0
$20,000
$250,000
$0
$0
$0 $270,000
Appropriated through 6/30/2026
Total Five Year CIP
Expenditure Type Design/Engineering Land Acquisition Vehicles/Equipment Construction
Total Project Cost
FY2027
FY2028
FY2029 FY2030 FY2031
$20,000 $250,000
20,000
$20,000 $250,000
250,000
$0 $0
$0 $0
Total Uses
$270,000
$0
$20,000
$250,000
$0
$0
$0 $270,000
Operating Impact
No operational impact is anticipated.
Town of Blacksburg
112
FY 2027-2031 Adopted
Made with FlippingBook Digital Proposal Maker