Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

EGIS

Department

Project Title

Glade Road Multi-modal Improvements

Status

New

Project Description

The goal of this project is to ultimately design a multi-use path connecting the University City Blvd area and the Glade Road area subdivisions to Heritage Park. The intiial funding is for a feasibility study and concept design to include in a future VDOT Revenue Sharing application.

Goal Addressed

Community Wellbeing

Estimated Start Date

Estimated End Date

7/1/2029

8/30/2030

Funded through 6/30/2026

Total Five Year CIP

Funding Sources

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

General Fund

$0 $0 $0 $0 $0 $0 $0 $0 $0

250,000

$250,000

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$0 $0 $0 $0 $0 $0 $0

VDOT Smart Scale

Other/Grants Total Sources

$0

$0

$0

$0 $250,000

$0 $250,000

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering

Total Project Cost

$0 $0 $0 $0 $0

250,000

$250,000

Construction

$0 $0 $0

Land Acquistion

Vehicles/Equipment

Total Uses

$0

$0

$0

$0 $250,000

$0 $250,000

Operating Impact