Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

EGIS

Department

Project Title

Clay Street Sidewalk & Roadway Improvements

Status

Existing

Project Description

This project is intended to provide a sidewalk connection along the south side of Clay Street from Church Street to Jefferson Street (approximately 2,600 feet) with adjustments to Clay Street to facilitate bike mobility and provide and improve storm drainage. The addition of sidewalk in this location will provide a connection between existing sections and complete the network along Clay Street. Curb, gutter and a drainage network will be added along the length of the project, as needed, and the roadway section will be widened, where applicable, to provide for appropriate on-road bike facilities. The addition of sidewalk and widening of the road will require stormwater management considerations and special attention will need to be given to the management of runoff due to the sensitive nature of the existing water shed. Small adjustments to the current Clay Street alignment, both vertical and horizontal, will be made to improve areas of poor sight distance and excess grade change.

Goal Addressed

Community Wellbeing

Estimated Start Date

Estimated End Date

current

12/31/2031

Funded through 6/30/2026

Total Five Year CIP

Funding Sources

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

General Fund

$0

150,204

173,964 308,618

$482,582

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$3,623,263

3,623,263 $3,623,263

$0 $0 $0 $0 $0

$0 $0 $0 $0 $0

$4,105,845

173,964 308,618 3,623,263 $4,105,845

VDOT Smart Scale

Other/Grants Total Sources

$150,204

$0

$0 $347,928 $617,236 $7,246,52 6 $8,211,6 90

$7,729,10 8

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering

Total Project Cost

$498,132 $7,863,76 2

150,204

347,928

$347,928

Construction

617,236 7,246,52 6 $7,863,76 2

Land Acquisition

$0 $0

$0 $0

Vehicles/Equipment

$8,361,89 4

Total Uses

$150,204

$0

$0 $347,928 $617,236 $7,246,52 6 $8,211,6 90

Operating Impact

Regular roadway / sidewalk maintenance.

Town of Blacksburg

107

FY 2027-2031 Adopted

Made with FlippingBook Digital Proposal Maker