Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
EGIS
Department
Project Title
Clay Street Sidewalk & Roadway Improvements
Status
Existing
Project Description
This project is intended to provide a sidewalk connection along the south side of Clay Street from Church Street to Jefferson Street (approximately 2,600 feet) with adjustments to Clay Street to facilitate bike mobility and provide and improve storm drainage. The addition of sidewalk in this location will provide a connection between existing sections and complete the network along Clay Street. Curb, gutter and a drainage network will be added along the length of the project, as needed, and the roadway section will be widened, where applicable, to provide for appropriate on-road bike facilities. The addition of sidewalk and widening of the road will require stormwater management considerations and special attention will need to be given to the management of runoff due to the sensitive nature of the existing water shed. Small adjustments to the current Clay Street alignment, both vertical and horizontal, will be made to improve areas of poor sight distance and excess grade change.
Goal Addressed
Community Wellbeing
Estimated Start Date
Estimated End Date
current
12/31/2031
Funded through 6/30/2026
Total Five Year CIP
Funding Sources
Total Project Funding
FY2027 FY2028 FY2029 FY2030 FY2031
General Fund
$0
150,204
173,964 308,618
$482,582
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$3,623,263
3,623,263 $3,623,263
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$4,105,845
173,964 308,618 3,623,263 $4,105,845
VDOT Smart Scale
Other/Grants Total Sources
$150,204
$0
$0 $347,928 $617,236 $7,246,52 6 $8,211,6 90
$7,729,10 8
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Total Five Year CIP
Expenditure Type Design/Engineering
Total Project Cost
$498,132 $7,863,76 2
150,204
347,928
$347,928
Construction
617,236 7,246,52 6 $7,863,76 2
Land Acquisition
$0 $0
$0 $0
Vehicles/Equipment
$8,361,89 4
Total Uses
$150,204
$0
$0 $347,928 $617,236 $7,246,52 6 $8,211,6 90
Operating Impact
Regular roadway / sidewalk maintenance.