Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

Public Works

Department

Project Title

Sidewalk Trip Hazard Removal

Status

Existing

Project Description

This project provides funding for sidewalk trip hazard removal for "severe" and "most severe" classes of hazards by grinding down sidewalk or replacing brick sidewalk tripping hazards via acceptable VDOT methods, where settlement exceeds 1/2 inch to 2 1/2 inches. Trip hazard removal projects bring sidewalks into compliance with the Town's ADA Transition Planning at a lower cost than full replacement. This project is eligible for a VDOT Revenue Sharing Program match.

Goal Addressed

Transportation

Estimated Start Date

Estimated End Date

Continuing

Continuing

Total Five-Year CIP

Funded through 6/30/2026

FY2027 FY2028 FY2029 FY2030 FY2031

Funding Sources General Fund

Total Project Funding

$62,500 Continuing

12,500 12,500 12,500 12,500 12,500 $62,500

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0

$62,500

12,500 12,500 12,500 12,500 12,500 $62,500

VDOT Smart Scale

Other/Grants Total Sources

$125,000

$0 $25,000 $25,000 $25,000 $25,000 $25,000 $125,000

Total Five-Year CIP

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Expenditure Type Design/Engineering

Total Project Cost

$0

$0

Construction

$125,000 Continuing

25,000 25,000 25,000 25,000 25,000 $125,000

Land Acquisition

$0 $0

$0 $0

Vehicles/Equipment

Total Uses

$125,000

$0 $25,000 $25,000 $25,000 $25,000 $25,000 $125,000

Operating Impact

No additional operational costs are anticipated.

Town of Blacksburg

106

FY 2027-2031 Adopted

Made with FlippingBook Digital Proposal Maker