PROJECT DETAILS/COST ESTIMATES
Public Works
Department
Project Title
Roadway Full Depth Reclamation (FDR)
Status
Existing
Project Description
This project provides funding for the reconstruction of town streets through the process of Full Depth Reclamation (FDR). FDR will be performed on streets where reconstruction is needed and where normal pavement maintenance activities do not apply. This process will provide recycling and reconstruction of the road base material, but with a cost that is a fraction of traditional road reconstruction. The VDOT Revenue Sharing Program does not always fund pavement maintenance activities that include asphalt pavement overlays. However, this process is considered to be road reconstruction and therefore is eligible for VDOT Revenue Sharing funds.
Goal Addressed
Transportation
Estimated Start Date
Estimated End Date
Continuing
Continuing
Total Five Year CIP
Funded through 6/30/2026
FY2027 FY2028 FY2029 FY2030 FY2031
Funding Sources General Fund
Total Project Funding
$1,000,000 Continuing
200,000 200,000 200,000 200,000 200,000 $1,000,000
General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
$1,000,000 Continuing
200,000 200,000 200,000 200,000 200,000 $1,000,000
VDOT Smart Scale
Other/Grants Total Sources
$2,000,000
$0 $400,000 $400,000 $400,000 $400,000 $400,000 $2,000,000
Total Five Year CIP
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Expenditure Type Design/Engineering
Total Project Cost
$0
$0
Construction
$2,000,000 Continuing
400,000 400,000 400,000 400,000 400,000 $2,000,000
Land Acquisition
$0 $0
$0 $0
Vehicles/Equipment
Total Uses
$2,000,000
$0 $400,000 $400,000 $400,000 $400,000 $400,000 $2,000,000
Operating Impact
No additional operational costs are anticipated.