Town of Blacksburg

PROJECT DETAILS/COST ESTIMATES

EGIS

Department

Project Title

Church Street Sidewalk Infill

Status

New

Project Description

This project includes the design and construction of a 5-foot wide and 120-foot long sidewalk, with grass buffer along the east side of Church Street at 307 Church Street.

Goal Addressed

Neighborhood Quality

Estimated Start Date

Estimated End Date

Summer 2027

Winter 2028

Funded through 6/30/2026

Total Five Year CIP

Funding Sources General Fund

Total Project Funding

FY2027 FY2028 FY2029 FY2030 FY2031

$0

$0

General Obligation Bonds Water & Sewer Fund Stormwater Fund Solid Waste Fund VDOT Revenue Sharing

$106,400

106,400

$106,400

$0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0

VDOT Smart Scale

Other/Grants Total Sources

$106,400

$0

$0 $106,400

$0

$0

$0 $106,400

Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031

Total Five Year CIP

Expenditure Type Design/Engineering

Total Project Cost

$10,000 $96,400

10,000 96,400

$10,000 $96,400

Construction

Land Acquisition

$0 $0

$0 $0

Vehicles/Equipment

Total Uses

$106,400

$0

$0 $106,400

$0

$0

$0 $106,400

Operating Impact

No operational impact is anticipated.