Town of Blacksburg
PROJECT DETAILS/COST ESTIMATES
Parks & Rec
Department
Project Title
Athletic Field U pgrades
Status
New
Project Description
All of the towns athletic facilities with the exception of the two fields at South Point Park were constructed over thirty years ago and lack modern amenities. This project will upgrade various athletic fields around town to include lights, field turf where applicable, scoreboards, irrigation, drainage, and other amenities. Town staff will engage a design consultant/engineer and go through a public engagement process to priortize field improvements including a conceptual design to refine the scope and cost of field upgrades.
Goal Addressed
Recreation
Estimated Start Date
Estimated End Date
Summer 2027
Summer 2029
Funded through 6/30/2026
Total Five Year CIP $10,000,000
Funding Sources General Fund
Total Project Funding
FY2027 FY2028 FY2029 FY2030 FY2031
$50,000
50,000 10,000,000
General Obligation Bonds Water & Sewer Fund
$10,000,000
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
Stormwater Fund Solid Waste Fund
VDOT Revenue Sharing VDOT Smart Scale
Other/Grants Total Sources
$10,050,000
$0 $50,000 $10,000,000 $0
$0
$0 $10,000,000
Appropriated through 6/30/2026 FY2027 FY2028 FY2029 FY2030 FY2031
Total Five Year CIP
Expenditure Type Design/Engineering Construction Land Acquisition Vehicles/Equipment
Total Project Cost
$550,000 $9,500,000
50,000 500,000
$550,000 $9,500,000
9,500,000
$0 $0
$0 $0
Total Uses
$10,050,000
$0 $50,000 $10,000,000 $0
$0
$0 $10,050,000
Operating Impact
Town of Blacksburg
83
FY 2027-2031 Adopted
Made with FlippingBook Digital Proposal Maker