Town of Blacksburg Adopted Operating Budget FY 2027
ENGINEERING AND GIS DEPARTMENT ENGINEERING DIVISION FUNDING SUMMARY
Actual
% Change
Expended FY 2025
Budget FY 2026
Budget FY 2027
From
FY 2026
Item Account Personnel Services
$
$
$
777,282 422,017 16,652 14,164 2,244 12,049 2,018 33,327
708,043 366,409 135,000 25,450 6,500 11,300
814,394 445,371 156,900 22,980 6,500 9,340 2,700 20,000
15.0% 21.6% 16.2% (9.7%) (17.3%) 100.0% (11.9%) 15.9% 0.0%
Benefits
Contractual Services
Supplies
Training and Travel Internal Services
Leases
-
Capital Outlay
22,700
Total
$ 1,279,753 $ 1,275,402 $ 1,478,185
Engineering Division Total FY 2027 Expenditures: $1,478,185
Capital Outlay 1.4%
Training and Travel 0.4%
Supplies 1.6%
Internal Services 0.6%
Contractual Services 10.6%
Leases 0.2%
Benefits 30.1%
Personnel Services 55.1%
PERSONNEL SUMMARY
Actual FY 2025
Budget FY 2026
Budget FY 2027
Authorized Position Administrative Specialist Director of Engineering
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 8.00
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 8.00
1.00 1.00 1.00 2.00 1.00 1.00 1.00
Engineer I Engineer II
Engineering Field Supervisor Inspector - Site Construction Senior Project Manager Water Resources Manager
-
Total
8.00
110