MBSE with Genesys 093022
Why Do Systems Engineering: The Financial Case • Cope with complexity • Avoid omissions • Avoid invalid assumptions • Make informed, defensible decisions • Manage change • Design most efficient, economic, and robust solution • Achieve greater design control Project Phase Method 1 — Bottom ‐ Up Cost Method 2 — Total Costs Breakdown Method 3 — Top ‐ Down Hypothetical Project Requirements 1 x 1 x 1 x Design 8 x 3 ‐ 4 x 4 x Build 16 x 13 ‐ 16 x 7 x Test 21 x 61 ‐ 78 x 28 x Operations 29 x 157 ‐ 186 x 1615 x Source: Error cost escalation through the project life cycle ‐ NASA Johnson Space Center It is not hard to know when system engineering fails, because when something important goes wrong it usually makes the news fast. INCOSE
23
Enabling Project Success: The Motivation for SE
Understanding the problem Integrating the team Defining the seams Addressing the gaps Guarding the why
Image Credit: Defense Acquisition University