MBSE with GENESYS 2024

Inserting Functions within the Parallel Construct

1. Drag “New Entity” and drop it on the left branch of the parallel construct 2. Accept the default “Function_004” as the name of the new Function 3. Drag “New Entity” and drop it on the right branch of the parallel construct 4. Accept the default “Function_005” as the name of the new Function 5. Drag “New Entity” and drop it on the main branch below the parallel 6. Accept the default “Function_006” as the name of the new Function

Which function will start first? Which function will end first?

367

Simulating the Parallel Construct 1. In the simulator, click Reset 2. Click Run The first function on each branch was enabled simultaneously All parallel branches must complete execution before rejoining and enabling the next function after the concurrency Scheduling (execution) decision for the parallel functions is deferred (“Don’t Care” sequence)

368

Made with FlippingBook - Online magazine maker