Create a RISK Element
Description: The requirement states that the system shall be staffed at a maximum of 20 personnel on any shift. This requirement will cause an operational risk because of the many different types of tasks that may be required to be performed concurrently by the system. Status Description: Unanalyzed Mitigation Plan: Institute a comprehensive training program in which each staff member can perform at least one half of the possible tasks. Mitigation Cost: 60000
NOTE: Completion of RISK on Secondary Tab (next slide)
Relation: “caused by”
159
RISK Element, Secondary Tab
Set Type: Other Set Consequence: 3 – Moderate Set Likelihood: 4 – High Likelihood Significance: Requires Further Review Set Date: March 16,2018
NOTE: Risk Rating can be set by script using program risk cube values when running Risk Report.