Risk
• Defined as the uncertainty of attaining or achieving a product or program milestone • May exist for several reasons • Budget or schedule constraints • High or leading edge technology • New designs or design concepts • Criticality to the user/customer • We capture this information by using the Risk Class
147
Handling CONCERNs in the design
• Create the new CONCERN (relating it to the element causing the CONCERN). • Take action to resolve the CONCERN. Generally this is done via a Trade Study or another engineering team action that can be documented (for example – a calculation, technical study, research, etc.). • Close the CONCERN based on the results of the engineering study or analysis. • Generate a “new” element in the architecture to reflect the decision (for example – a new requirement or constraint on the system design).